स्थापत्य अभियांत्रिकी सराव प्रश्नपत्रिका क्रमांक ८ | Civil Engineering Practice Test 8

Civil Engineering Practice Test 8

Telegram Group Join Now
Join Instagram Join Now

Civil Engineering Practice Test 8:  We are starting Civil Engineering practice question paper according to the new syllabus and changing exam patterns. In this, we are going to take important “Topics” practice questions for Civil Engineering Technical Subject. So let’s begin………

Civil Engineering Questions and Answers | Civil Engineering Objective Questions and Answer

स्थापत्य अभियांत्रिकी सराव चाचणी ८ : आम्ही नवीन अभ्यासक्रमानुसार आणि बदलत्या परीक्षेच्या पद्धतीनुसार स्थापत्य अभियांत्रिकी सराव प्रश्नपत्रिका सुरू करत आहोत. यामध्ये आपण स्थापत्य अभियांत्रिकी तांत्रिक विषयासाठी महत्त्वाचे “विषय” सराव प्रश्न घेणार आहोत. चला तर मग सुरुवात करूया……..

तसेच या संदर्भातील पुढील सर्व अपडेट्ससाठी या लिंक वरून आपण आमच्या टेलिग्राम चॅनलला जॉईन करावे किंवा या लिंक वरून महाभरती एक्सामची अधिकृत अँप आपल्या मोबाईल मध्ये डाउनलोड करावी आणि अधिक ताज्या आणि अधिकृत महाराष्ट्र परीक्षेच्या अपडेटसाठी MahaBharti.in/exam फॉलो करा:

Click Here For All Civil Engineering MCQ Practice Tests For Maharashtra Exam

1980
Created on By MahaBharti Exam Team
Civil Engineering Practice Test 4

Civil Engineering Practice Test 8

महाराष्ट्रातील सर्व भरती परीक्षेस उपयुक्त नवीन IBPS/TCS पॅटर्न नुसार प्रश्न

1 / 15

When a rectangular beam is loaded transversaly the maximum compressive stress develops on

2 / 15

Shear force for a cantilever carrying a uniformely distributed load over its length, is

3 / 15

The cubic content of concrete (1 : 2 : 4) for the road specified in _____

4 / 15

The interrelationships between the functional elements of a programed is achieved through _____

5 / 15

Along the principal plarr subjected to maximum principal stress ______

6 / 15

Along the principal plarr subjected to maximum principal stress ______

7 / 15

The types of pumps used in tube wells are _____

8 / 15

The moment diagram for a cantilever whose free end is subjected to a bending moment, will be a

9 / 15

The detention period in a septic tank is assumed

10 / 15

Anti-siphonage pipe is connected to ____

11 / 15

A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is ____

12 / 15

If the shear force along a section of a beam is zero, the bending moment at the section is

13 / 15

The activity-oriented technique is _____

14 / 15

The 'centre line method' i specially adopted for estimating _____

15 / 15

When a rectangular beam isloaded longitudinally shear develops on _____

Your score is

The average score is 37%

0%

Leave a Comment


Available for Amazon Prime