स्थापत्य अभियांत्रिकी सराव प्रश्नपत्रिका क्रमांक १० | Civil Engineering Practice Test 10

Civil Engineering Practice Test 10

Telegram Group Join Now
Join Instagram Join Now

Civil Engineering Practice Test 10:  We are starting Civil Engineering practice question paper according to the new syllabus and changing exam patterns. In this, we are going to take important “Topics” practice questions for Civil Engineering Technical Subject. So let’s begin………

Civil Engineering Questions and Answers | Civil Engineering Objective Questions and Answer

स्थापत्य अभियांत्रिकी सराव चाचणी १० : आम्ही नवीन अभ्यासक्रमानुसार आणि बदलत्या परीक्षेच्या पद्धतीनुसार स्थापत्य अभियांत्रिकी सराव प्रश्नपत्रिका सुरू करत आहोत. यामध्ये आपण स्थापत्य अभियांत्रिकी तांत्रिक विषयासाठी महत्त्वाचे “विषय” सराव प्रश्न घेणार आहोत. चला तर मग सुरुवात करूया……..

तसेच या संदर्भातील पुढील सर्व अपडेट्ससाठी या लिंक वरून आपण आमच्या टेलिग्राम चॅनलला जॉईन करावे किंवा या लिंक वरून महाभरती एक्सामची अधिकृत अँप आपल्या मोबाईल मध्ये डाउनलोड करावी आणि अधिक ताज्या आणि अधिकृत महाराष्ट्र परीक्षेच्या अपडेटसाठी MahaBharti.in/exam फॉलो करा:

Click Here For All Civil Engineering MCQ Practice Tests For Maharashtra Exam

1351
Created on By MahaBharti Exam Team
Civil Engineering Practice Test 4

Civil Engineering Practice Test 10

महाराष्ट्रातील सर्व भरती परीक्षेस उपयुक्त नवीन IBPS/TCS पॅटर्न नुसार प्रश्न

1 / 15

For ensuring quality of concrete, use ______

2 / 15

The distribution system configuration shown in the figure given is called

3 / 15

The source of surface water is from ______

4 / 15

Biochemical Oxygen Demand (BOD) of sewage is the _____

5 / 15

Colours of fresh and septic sewage respectively are ______

6 / 15

In two dimensional incompressible steady flow around an airfoil, the stream lines are 2 cm apart at a great distance from the airfoil, where the velocity is 30 m/sec. The velocity near the airfoil, where the stream lines are 1.5 cm apart, is

7 / 15

Under natural conditions of flow, an unpolluted river would contain ______

8 / 15

The waste stabilization ponds can be

9 / 15

Permissible compressive strength of M 300 concrete grade is

10 / 15

M 10 grade of concrete approximates

11 / 15

The total domestic consumption in a city water supply is assumed as

12 / 15

The standard sand now a days used in India, is obtained from _______

13 / 15

The source of surface water is from ______

14 / 15

Pathogenic bacteria, enter wastewaters, primarily from _____

15 / 15

A water supply scheme has to be designed for a city having a population of 1,00,000. If annual average daily consumption of water is 250 lpcd, then maximum daily draft will be

Your score is

The average score is 45%

0%